Road resurfacing: St Asaph Avenue, Kinmel Bay, 28 April - 2 May

Roadworks
Work starts: Monday 28 April 2025
Work finishes: Friday 2 May 2025
What is happening?
We are resurfacing St Asaph Avenue from south of the junction with the A548 to the junction with Cader Avenue (over the railway bridge).
Our contractor will be working from 7am to 2am. We will need to close sections of the road at times to complete this work. Signposted diversions and convoy working will be in place.
Will it affect parking?
Yes - there will be no parking on affected sections while we do this work.
We will maintain pedestrian access at all times.
What is resurfacing?
Step 1 - remove the existing surface (this is called planing)
Step 2 – Adjust or replace the ironwork, manholes & drainage gullies
Step 3 - clean the surface with a mechanical sweeper
Step 4 - lay a bond coating, to make sure the new surface sticks
Step 5 - lay the new surface
Step 6 - compact and level the new surface with rollers
Step 7 - repaint the road markings
Resurfacing is a noisy and dusty process, and we are sorry for the inconvenience this might cause. The new road surface will provide a smoother, quieter ride and will be a long lasting benefit to the community.
Questions?
If you need more information, please contact the Environment, Roads & Facilities Advice Team on erf@conwy.gov.uk or call 01492 575337.
Thank you for your patience while our contractor carries out this work.
Posted on 23/04/2025